Four Out of 10 Ain't Bad: St. Croix Crossing Bridge Pier Progress
MnDOT issues a new diagram showing how far along construction work is every Wednesday.
Here's the latest diagram showing how far along the foundations are for the new St. Croix River bridge.
According to the St. Croix Crossing project website:
"As of Nov. 20, all of the caissons, six of the 10 footings and five of the 10 columns are filled with concrete. Four of the 10 piers are complete!"
Check out the progress live at the St. Croix Crossing webcam.
Related:- Bridge Foundations on Track to Be Done in Early 2014
- Lunda/Ames Looks Like Low Bidder on St. Croix Bridge
- How St. Croix Crossing Crews Move Dirt Quickly
- Take a Virtual Trip through New Landscape at Hwy. 36 and Hwy. 95
- See St. Croix Crossing Construction Up Close
- Foundations about Two-Thirds Poured for St. Croix Crossing
- New Aerial Photos: A Bridge Rises on the St. Croix River
Find out what's happening in Stillwaterwith free, real-time updates from Patch.
Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.
We’ve removed the ability to reply as we work to make improvements. Learn more here