MnDOT: 'Main Reason' for $676 Million Cost of St. Croix River Crossing Project is Muck

Foundation work for the St. Croix River Crossing Project will account for about 40 percent of the estimated $676 million bridge project, MnDOT officials told the Pioneer Press.

The main reason the St. Croix River Crossing Project will cost nearly three times the amount spent to replace the Interstate 35W Bridge in Minneapolis is apparently, muck.

MnDOT estimates that the project will cost anywhere between $571 million to $676 million to complete.

Foundation work for the new bridge accounts for 40 percent of that estimate, Project Manager Jon Chiglo told the Pioneer Press. Crews are expected to have to drill down 160 feet to complete foundation work in the St. Croix River, which is about 70 feet deeper than the longest shaft drilled for the I-35W bridge.

Find out what's happening in Stillwaterwith free, real-time updates from Patch.

"In some instances, we have 85 feet of muck in the St. Croix that we have to drill through before we reach the softer sandstone," Chiglo told the Pioneer Press. "And then there's 30 to 40 feet of soft sandstone that we'll go through and, ultimately, get into that more sound bedrock that we have to go into about 30 to 40 feet."

Click here to read the full report on TwinCities.com.

Find out what's happening in Stillwaterwith free, real-time updates from Patch.

is expected to start toward the end of May and last about three months. .

Do you think MnDOT will deliver this project at $676 million?

Is this the first time you’ve heard that “muck” was the reason the new bridge will cost almost three times more than the I-35W Bridge?

What do you think of this news?

Share your thoughts in the comment section below.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here